SDG&E Pipeline Safety Enhancement

Project Description
San Diego Gas and Electric (SDG&E) will be pressure testing and replacing portions of their gas pipeline system in the San Diego area. The portion of their program that affects the City of La Mesa will be performed in three phases.

Phase 49-15 Section 1 is located along Fletcher Parkway between Jackson Drive and Amaya Drive.  Section 2 starts on Amaya Drive at Fletcher Parkway running east to Primrose Drive and continuing easterly on Murray Drive to the eastern city limits into the City of El Cajon.  This phase consists of a 10-inch pipeline replacement with two new regulator stations at the Fletcher Parkway/Jackson Drive intersection and Fletcher Parkway/SR 125 underpass. This phase is scheduled to begin in October of 2015.

Phase 49-16 begins on Alvarado Road and continues south along I-8, down Baltimore Drive to University Avenue through the Civic Center and continuing south down Date Avenue to Orange Avenue. This phase includes hydro-testing and replacement of a 16-inch pipeline and is scheduled for the 4th quarter of 2015.

Phase 49-17 begins at the west end of the City on Alvarado Road and continues east to Baltimore Drive. This phase of construction consists of a 16-inch pipeline replacement. 

Contact Information


SDG&E


Jerry Butkiewicz
858.654.1507