SDG&E Pipeline Safety Enhancements

NOTICE OF CONSTRUCTION

SDG&E Pipeline Safety Enhancement Project - Baltimore Drive / University Avenue / Date Avenue



Project Description


Replacement of the 16” gas pipeline on Baltimore Drive, University Avenue and Date Avenue.Construction activities will include trench excavation, pipeline installation, and paving. SDG&E's contractor is scheduled to begin construction work on March 13 and conclude in July 2017.

Project Location


This phase of construction will start at Date Avenue and end just North of the intersection at Baltimore Drive and El Cajon Boulevard.

Project Schedule


Construction work will be completed in phases based on the construction phasing schedule.

Additional Information


For information about road closures and construction times, please refer to the Notice from SDG&E.  Contact Cameron Durckel, Public Affairs, SDG&E at 858.636.5781 with any questions.

Construction Phasing Map


Phasing Map